ILOILO — The Energy Regulatory Commission has approved the application of Jin Navitas Solaris Inc. to build and own the connection facilities for its Ajuy 1 Solar Power Plant in Iloilo. The decision, issued on September 24, clears a major regulatory hurdle before the facility can deliver power to Panay.
A Milestone for Panay’s Renewable Energy
The approval marks a significant step toward reducing the island’s reliance on fossil fuel plants and power imported from other grids. By adding local solar generation, the project supports the government’s renewable energy targets and enhances energy security for the region.
The plant will connect to the National Grid Corporation of the Philippines’ Concepcion–Sara 69-kilovolt transmission line. The dedicated point-to-point facilities will link the solar farm directly to the grid, ensuring efficient power delivery once commercial operations begin.
Ownership and Operational Responsibilities
Under the ERC ruling, Jin Navitas Solaris will own the take-off substations and related equipment. The National Grid Corporation will operate and maintain these facilities, with the developer paying the applicable charges. This arrangement keeps the connection cost as a project expense rather than adding to the grid’s regulated assets.
The connection works carry a cost of PHP 636.2 million. The developer must also pay a permit fee of PHP 4.77 million within 15 days. These financial details reflect the scale of the infrastructure required to integrate the solar plant into the existing transmission network.
Employment and Economic Impact
During peak construction, the project employed more than 700 workers, many from Ajuy and neighboring towns. The plant sits in Barangays Central and Tipacla, covering a significant area of farmland. The project broke ground in July 2025 and forms part of a larger PHP 2.37-billion investment.
The facility is being built in phases under the Department of Energy’s Green Energy Auction Program. The first phase targets commercial operation by late November 2026, later than the developer’s earlier June target. The remaining phases will follow in subsequent periods.
Toward Commercial Operation
Once completed, the Ajuy 1 Solar Power Plant is expected to become the largest solar facility in Panay. It has been recognized by the national government and the Department of Energy as an Energy Project of National Significance. The plant’s capacity is approximately 50 megawatts, with a peak output of 62 megawatts.
The project represents Iloilo’s first major ground-mounted solar installation. It adds clean power to the Panay grid and supports the province’s transition toward a more sustainable energy mix. The facility will help stabilize supply during peak demand periods.
A Glimpse Into Panay’s Energy Future
As more renewable energy projects come online, the question of how much solar can reshape Panay’s electricity landscape becomes increasingly relevant. The Ajuy project offers a tangible example of that potential. Its progress will be closely watched as it moves toward commercial operation later this year.